Project Plan Update
Motorola Timeline - City of Apopka Mesh Project Plan - January 2010

  • Installation of Planned Devices/Sites (Complete)  October 2009

  • Network Optimization (Complete)  November 2009

  • Performance Audit (Complete)  December 2009



  • Current Status
482 devices / sites installed
450 connected remaining 32 sites awaiting power, fill-in IAP backhaul or relocation
Alarms counts average in the signal digits and approximately 1-2% of network


  • Remaining Deployment (in progress) January 2010 **
Errol Estates (deploying!)
Design completed, 37 devices/sites and equipment is awaiting installation
12 devices installed, 6 connected to WMS, 25 to go awaiting PE pole swaps


  • Wekiva Glen (pending)
Preliminary designed completed (12 devices/sites)
Awaiting HOA approval from 1/14 HOA Board Review


  • Performance Audit Report Presentation (Jan 21st)
Evaluation of Fill-in devices / sites (in progress)
Site Survey of Potential Sites (in progress)
Selection & Schedule of Remaining Fill-In Site Deployment (in progress)


  • Punchlist items (in progress)
  IAP Pole Surge/Grounding Upgrades (in progress)
  Canopy CMM/AP Surge/Grounding (currently being scheduled)
  City Technical Staff Training for MotoMESH and WMS (Jan 25th & 26th)


  • Transition into Service (in progress, rolling migration)
Phase 1 – PTP and Canopy CMM / AP equipment under monitor and service mode.


  • Remaining Deployment (in progress) February 2010 **
Errol Estates (completing)
Wekiva Glen (TBD based on HOA approval)
Punchlist items (in progress)
IAP Pole Surge/Grounding Upgrades (completing)
Canopy CMM/AP Surge/Grounding (completing)
Design/Implementation of Remaining Fill-In Sites from Performance Audit (in progress)
Transition into Service (in progress, rolling migration)
Phase 2 – Canopy SM & Prizism application under monitor and service mode
Local Device Reset


  • Remaining Deployment (in progress) March 2010 **
Wekiva Glen (TBD based on HOA approval)


  • Punchlist items (completing)
Remaining Implementation of Fill-In Sites from Performance Audit (completing) (dependant on supply of power from PE)


  • Transition into Service (completing)
Phase 3 – MotoMESH Devices and WMS under monitor and service mode.


  • 2 Year Warranty

** Completion subject to and dependent upon power supplied and pole swaps completed by Progress Energy